What were the main challenges?
The main challenge was that the waste was on the first floor. We had to protect the staircase and take all the waste down 2 flights.
The other challenge was that the building was occupied. This meant that there were restrictions on when we could take the waste out and perform noisy operations.
Strip out included:
As part of the strip out we had to remove the following:
- Ceiling grid
- Ceiling tiles
- Partitions (plasterboard / glass / wood)
- Carpet tiles
- Reception desk/area and tiled flooring
- Office furniture
Waste removed included:
The kinds of waste materials that we had to take away were:
- Cables
- Tiles
- Rubble
- Plasterboard
- Timber
- Carpet tiles
- Plastic
- Metals