Responsible for stripping-out a 4th-floor office in Leeds with no lift access and ensuring all of the waste was tipped at fully licensed waste transfer stations within Leeds.

What were the main challenges?

The main challenge of completing the project was that the office was located on the 4th floor and lift access was not allowed. Therefore. we had to protect and the stairwell before the project started and maintain this protection throughout the works.

Strip out included:

As part of the strip out we had to remove the following:

  • Plasterboard partitions
  • Glass partitions
  • Blinds
  • Windowsills
  • Carpet tiles
  • Pillar boxing in
  • Suspended ceilings, grids / tiles
  • Kitchen including appliances
  • Internal doors
  • Cables, power and ethernet
  • Skirting boards
  • Bulk heads
  • Trunking
  • Office furniture

Waste removed included:

All of the waste generated by the strip-out was removed by our own Yes Waste teams and disposed of at fully licensed waste transfer stations within Leeds. The kinds of waste materials that we had to remove included:

  • Cables
  • Tiles
  • Rubble
  • Plasterboard
  • Timber
  • Carpet tiles
  • Plastic
  • Metals