21st March 2020

Case Study: Office soft strip demolition in Liverpool

Appointed as the contractor for a multi-phased soft strip demolition at an office in Liverpool, with all of the waste being tipped at fully licensed waste transfer stations.

What were the main challenges?

The main challenge was that the waste was on the first floor. We had to protect the staircase and take all the waste down 2 flights.

The other challenge was that the building was occupied. This meant that there were restrictions on when we could take the waste out and perform noisy operations.

Strip out included:

As part of the strip out we had to remove the following:

  • Ceiling grid
  • Ceiling tiles
  • Partitions (plasterboard / glass / wood)
  • Carpet tiles
  • Reception desk/area and tiled flooring
  • Office furniture

Waste removed included:

The kinds of waste materials that we had to take away were:

  • Cables
  • Tiles
  • Rubble
  • Plasterboard
  • Timber
  • Carpet tiles
  • Plastic
  • Metals